Because of the amount of information on our Capital Improvement Project Plan, this post is written as an outline rather than in narrative form.
Capital Improvement Projects (CIP) Overview: Timeframe, Inputs and Individual Project Approval
- The Capital Plan is a 20-year document compiling all the infrastructure needs for this time period.
- Each department (water, electric, etc.) has a master plan. This plan outlines what subject matter consultants, independent of the city, recommend the city do to keep infrastructure functioning at high service levels.
- Master plans are further supported by facilities plans, and specific assessments required outside of the master plan planning period.
- These plans are the source document for the full list of CIP projects.
- The first two years has the most refined project estimates based on the stage of their engineering.
- Final Engineering Phase and Construction will be more refined than those projects in Beginning Engineering.
- Projects estimated in the master plans will include a 30% contingency with an accuracy range of -50% to + 30% à This is due to the lack of scope elements that become available as the planning moves through engineering phases.
- It follows that as the timing extends into out years, the estimates are still being worked as project scopes and needs are better defined.
- Next, the budget process only allocates funding to the two-year portion of the Capital Improvement Plan, not the full 20.
- Remember the out-year project cost estimates are conceptual. As the work scope is better defined the estimates will be honed. Project costs are refined as they go through engineering phases.
- Additionally, priorities and needs change. The out-year projects also change.
- For example, you know you need a roof in 5 years. In that year five, the roof may be doing great, but the furnace needs to be replaced. Clearly the plan gets shuffled. Similar on a larger scale with CIP.
- Our CIP list acts like an ideal list. The plan includes the projects our city departments would like to accomplish, again, based on their respective master plans.
- Some are driven by regulatory needs, others by end-of-life cycle, others still are lower priority.
- Note: Public Works has added categories to help identify projects that are regulatory, capacity, deficient, or end of life cycle.
- Not all will be approved and completed.
- Some are driven by regulatory needs, others by end-of-life cycle, others still are lower priority.
- It follows that, though the list is approved the projects on that list are NOT considered approved.
- Each project must come before council at all stages of the project, from concept, design, detailed engineering, contracting and build. At any point council can vote down the project.
- We saw this a few years back with Nevada Street Bridge. The bridge was on the list. However, the project was not approved.
Council’s Vote on the CIP Plan and What it Means:
IMPORTANT:
- Regardless of Council’s vote, the plan is still loaded into the Budget.
- Regardless of Council’s vote, the first two years of the plan are allocated funds.
Impacts Ashland’s ability to access funding resources:
Lenders and grantors look at the council’s acceptance or rejection of the CIP plan in their funding decisions.
Many institutions require a commitment to the CIP plan from the local jurisdiction to secure funding.
- If the council does not support the plan lenders charge higher rates for funding
- Likewise, institutions may deny funding applications all together
- It is as if acceptance of the plan acts like a credit rating of 750 and helps secure low-cost funding IF needed.
- Conversely, rejection of the plan makes the city a higher credit risk, increases the cost to borrow, and may result in not receiving funding at all.
Grants:
- Grantors ask municipalities “is this project in an adopted plan.”
- If the CIP is not accepted, then the answer to this question is “no” and the ability to obtain the grant is subsequently diminished.
- Example: This situation is similar to trying to put an offer in on a home but not having a pre-qualifying letter.
Impacts to Alternate Revenue Streams:
- Projects in the CIP include tasks needed to prepare property for designation as surplus and subsequent sale.
- Such sales generate one time revenue resulting for disposition of the property.
Increased cost due to regulatory non-compliance, deferred maintenance, and emergency repair:
- Failing to meet regulatory requirements due to deferred maintenance results in fines and potential lawsuits.
- Emergency repairs, as compared to pre-planned repairs, have greater adverse impacts on rate payers due to their emergent nature an unpredictable timing.
- Similar to if a homeowners cleanout cap is broken and the homeowner puts off repair. When the line backs up, and it is a holiday, it will be comparatively more expensive to have the plumbing issue repaired.
- The expense is driven not only be timing but a repair that is more complex than the initial broken cleanout cap.
Well done, I knew some of this but I learned much. The format was excellent for getting the information simply and quickly.
LikeLike
Thank you for taking the time to read through!
LikeLike